2024 Europa League Champions Betting Odds Chicago’s Leading Electrical Contractor Wed, 09 Sep 2020 13:36:19 +0000 en-US hourly 1 https://wordpress.org/?v=6.5.3 /wp-content/uploads/2020/09/cropped-favicon-32x32.png 2024 Europa League Champions Betting Odds 32 32 2024 Europa League Champions Betting Odds /project/lv-office-space/ /project/lv-office-space/#respond Wed, 09 Sep 2020 13:27:46 +0000 /?post_type=project&p=574 The post LV Office Space appeared first on Continental Electrical Construction Company.

]]>

LV Office Space

This office environment includes multiuse space for the client, including common seating areas, offices, conference rooms, and individual desk space. Each space was fitted with low voltage solutions, including pendant speakers and wireless access points. The office space also required the installation of two IDF closets.

Services Performed: IDF Closets, Wireless Access Points, Sound Systems

Square Feet: 109,500

Feet of Cable: 218, 500

Pendant speakers installed: 52

Wireless Access Points (WAPs installed): 32

Low Voltage Office Space Project
Low Voltage Office Space Project
Low Voltage Office Space Project

Commercial Projects

One of Continental’s specialties is the design and construction of commercial buildings — projects that have to deliver efficiency, sophisticated performance and aesthetic appeal. Today’s office environments are architecturally unique and include specialized electrical, structured cabling, security, and audio and video systems that need to be integrated and mobilized quickly to ensure operational efficiency.

The post LV Office Space appeared first on Continental Electrical Construction Company.

]]>
/project/lv-office-space/feed/ 0
2024 Europa League Champions Betting Odds /project/healthcare-center/ /project/healthcare-center/#respond Wed, 09 Sep 2020 13:21:10 +0000 /?post_type=project&p=569 The post Healthcare Center appeared first on Continental Electrical Construction Company.

]]>

Healthcare Center

For this project, we provided all the low voltage for a brand-new procedure center at a hospital in the south suburbs of Chicago. Our low voltage team provided solutions in the procedure rooms, recovery bays, nursing stations, and the IDF closets.

Services Performed: IDF closets, low voltage solutions

Square Feet: 45,700

Feet of Cable: 470,000

Work Hours: 3,136

healthcare center project
healthcare center project
healthcare center project

Healthcare Projects

Healthcare customers are unique in their critical requirements for electrical construction services. Continental consistently performs quality health care solutions that ensure the health and safety of patients. We have worked on facilities administering to hundreds of patients and those helping one life at a time. These include MRI and CAT scan facilities, obstetrics wings, cardiac labs, emergency rooms, dialysis departments, rehabilitation centers and medical support buildings.

The post Healthcare Center appeared first on Continental Electrical Construction Company.

]]>
/project/healthcare-center/feed/ 0
2024 Europa League Champions Betting Odds /project/caterpiller-hq/ /project/caterpiller-hq/#respond Thu, 19 Mar 2020 15:58:24 +0000 http://cecco.wpengine.com/?post_type=project&p=267 The post Caterpiller HQ appeared first on Continental Electrical Construction Company.

]]>

Caterpiller HQ

In this project, Continental was tasked with building out 2.5 floors of high-end tenant space with one server room and 4 IDF rooms, with sound masking in all open areas. We provided a complete end to end CommScope Systimax Certified solution. Category 6 to work areas and Category 6A to wireless access points. This was a face-paced project with a short complete schedule, based on the need for a corporate move. We completed the project in December of 2017.

Owner:
Caterpillar

Services Performed:
Telecommunications Structured Cabling, Sound Masking

Square Feet:
90,000

Design:
272,000 ft of Cat 6 plenum cable
800 workstations
1,600 RJ45 jacks

Structured Cabling

Continental is the single-source provider of network cabling infrastructure for all facets of the enterprise. The end result is an optimized IT performance that reduces overall structured cabling costs and improves efficiencies across the entire enterprise.

The post Caterpiller HQ appeared first on Continental Electrical Construction Company.

]]>
/project/caterpiller-hq/feed/ 0
2024 Europa League Champions Betting Odds /project/zurich-hq/ /project/zurich-hq/#respond Thu, 19 Mar 2020 15:46:11 +0000 http://cecco.wpengine.com/?post_type=project&p=261 The post Zurich HQ appeared first on Continental Electrical Construction Company.

]]>

Zurich

Continental installed approximately (5500) data locations on 12 floors of tenant spaces, as well as a fitness center and a cafeteria. For this complete CommScope Systimax Certified Solution, we built out 34 IDFs & 1 MDF within a nine-month schedule, which took 20,250 field hours. Prefab assembled 95 2-post equipment racks containing labeled patch panels, fiber enclosures and both vertical & horizontal cable managers at approximately 350 prefab hours

During base build construction, CECCo developed a customer relationship with Zurich and continues to do any moves, adds, & changes. The base build was completed in October of 2016.

Owner:
Zurich

Services Performed:
Complete Structured Cabling Solution

Square Feet:
783,800

Design:
1.5 million ft of cable
82,000 ft of fiber
10,000+ jacks

Structured Cabling

Continental is the single-source provider of network cabling infrastructure for all facets of the enterprise. The end result is an optimized IT performance that reduces overall structured cabling costs and improves efficiencies across the entire enterprise.

The post Zurich HQ appeared first on Continental Electrical Construction Company.

]]>
/project/zurich-hq/feed/ 0
2024 Europa League Champions Betting Odds /project/cyrus-one-dc2/ /project/cyrus-one-dc2/#respond Thu, 19 Mar 2020 15:40:36 +0000 http://cecco.wpengine.com/?post_type=project&p=256 The post Cyrus One DC2 appeared first on Continental Electrical Construction Company.

]]>

Cyrus One DC2

Continental built out 200,000 square feet of a new data center, including all fiber optic backbone cabline from the existing NetPop infrastructure to (2) Meet Me Rooms and (7) IDF’s. We also installed all card access and camera cabling for this project. This project was completed in October of 2017.

Owner:
Cyrus One

Services Performed:
Fiber backbone, Cat6 cabling, card access, camera cabling

Square Feet:
200,000

Design:
125,000′ Cat6 Cable
33,000′ composite security cable
18,000′ fiber used

Structured Cabling

Continental is the single-source provider of network cabling infrastructure for all facets of the enterprise. The end result is an optimized IT performance that reduces overall structured cabling costs and improves efficiencies across the entire enterprise.

The post Cyrus One DC2 appeared first on Continental Electrical Construction Company.

]]>
/project/cyrus-one-dc2/feed/ 0
2024 Europa League Champions Betting Odds /project/1-s-dearborn/ /project/1-s-dearborn/#respond Thu, 19 Mar 2020 15:34:05 +0000 http://cecco.wpengine.com/?post_type=project&p=250 The post 1 S Dearborn appeared first on Continental Electrical Construction Company.

]]>

1 S Dearborn: DAS installation

For this project, we provided installation of a Verizon Distributed Antenna System throughout the 40-story building including the conduit pathway installation. We also installed Verizon headend main equipment room. Sweep and PIM testing provided for commissioning. Project completed in June of 2016.

Owner:
Verizon, MRFS integrator

Services Performed:
Distributed Antenna System

Square Feet:
828,538

Design:
12 x 12 x 6 JB for 297 antennas
8 x 18 x 6 JB for 265 splitters
21,000′ of 1/2″ coaxial cables

Structured Cabling

Continental is the single-source provider of network cabling infrastructure for all facets of the enterprise. The end result is an optimized IT performance that reduces overall structured cabling costs and improves efficiencies across the entire enterprise.

The post 1 S Dearborn appeared first on Continental Electrical Construction Company.

]]>
/project/1-s-dearborn/feed/ 0